Summary

Work Tracking

Team Work - Detailed

Paul Larson (plars)

Progress:

  • Reviewed specifications within the Infrastructure team
  • Drafting PatchTracking specification

  • Tested some Stable Release Updates for Maverick that affect Linaro
  • Wrote a version of the headless testplan for ISEE IGEP (Cortex A8) board, found someone with an IGEP board to make sure it looks sane
  • Some other corrections to test cases linked to from qatracker
  • Testing for final images
  • Brought our first QA person on board - had a startup meeting with him
  • Worked some more on scripts to automate the detection and download of the latest image and hardware pack.

Issues:

  • I need hardware - I have only a beagle c4 which will not even run all of the images successfully, and does not lend itself well to some things I'd like to try for automation

Plans:

  • Starting another new person next week
  • Finish drafting/reviewing Infrastructure team specs
  • More testing and automation work

James Westby (james_w)

Progress:

  • Reviewing Infrastructure team specs.
  • Establishing the scope of the status reporting task
  • Managing the addition of new team members.

Issues:

  • None currently.

Plans:

  • More reviews and drafting.
  • Write the notes from the Android session

Zygmunt Krynicki (zyga)

Progress:

Plans:

  • Push JSON schema changes for review
  • Push linaro-json-xmlrpc to a PPA
  • Get an approval for the other-linaro-n-test-result-display-in-launch-control
  • Discuss about what to do with other-linaro-n-benchmark-reports-in-launch-control and complete review.

Issues:

  • Early review feedback from Michael Hope suggests that our solution may not be appropriate and further investigation is required.

Michael Hudson (mwhudson)

Progress:

Plans:

  • A little bit more spec writing.
  • (arm-m-image-building-console)
    • Finish off three remaining work items:
      • "Contents of the notifications must be templated"
      • "unify configs (config/lexbuilder.cfg, config/*.config, settings{,_devel,_production}.py) as far as reasonably possible"
      • "Fix deployment path. Currently deployed to /srv"
    • (the last two are likely to be solved with the same branch)
    • Have a very serious look through the bugsy codebase to see if we've missed anything with respect to open sourcing.
  • Work with Ian to try to arrange hardware for OurOwnOffspring.

  • (other-linaro-n-image-building)
    • Work on modifications to hwpacks to allow more than one to be installed at once. Lower priority than other tasks, so may not make much progress.

Issues:

  • Lack of hardware for OurOwnOffspring -- some images can be built under qemu but not all (at least netbook-efl fails because of bug Launchpad bug #530000 "mono assembly installation under qemu-arm-static hangs", which is marked "Won't Fix" basically because it's too hard :()

  • Waiting for the creation of the offspring project in Launchpad.

Guilherme Salgado (salgado)

Progress:

  • Finished first draft of ContinuousIntegration and PackageDevelopmentTools

  • Investigated using sbuild+xdeb to do cross builds for PackageDevelopmentTools

  • UI reviews for Launchpad
  • Tested the image that became the 10.11 release

Issues:

  • None currently.

Plans:

  • Draft work items for my specs and for ImproveLinaroMediaCreate

  • Start working on ImproveLinaroMediaCreate, together with Mirsad

Deepti Kalakeri (deepti)

Progress:

Issues:

Plans:

Mirsad Vojnikovic ()

(Mirsad joined the Infrastructure team this week)

Progress:

  • going through initial tasks to enable my Linaro work, still one or two to issues resolve
  • tested headless 10.11 RC image on U8500, but not reported results yet - will be done ASAP

Issues:

Plans:

Ian Smith (ismith)

Progress:

  • Work on a consolidated report
  • Reviewing Infrastructure specifications
  • Establishing how best to help with the conference calls for the next 10 days or so.
  • Looking at hwpack licencing (again)!
  • Reporting
  • Assisting with Linaro IS requests

Issues:

  • Struggling with problems from Maverick update - no more hibernate, Skype or Mumble for now - and my first Ubuntu crash :-(

Plans:

  • Reporting
  • Conference call assistance
  • Updating personnel "database"
  • Finishing hwpack licence (at last!)

internal/archive/Platform/LAVA/Infrastructure/Status/2010-11-11 (last modified 2013-08-23 12:19:23)