Timeline for delivery of big.LITTLE Switcher (Task Migration) on Fast Model

Milestones Status

Plan of Record

Milestone

Date

Current

Last Report

Issue

Develop Reference Switcher

3/15/2012

Validation Ready

3/29/2012

Validate Ref. Switcher

4/5/2012

Develop Integrated Switcher

4/05/2012

Validate Integrated Switcher

4/26/2012

Model-RC-1

5/10/2012

Model-GA Release

5/31/2012

Color Keys

Complete

On target

At risk
mitigation in place

Will miss target
Immediate action required

Blueprints Status

Accomplishments This Week

  • Model-RC1 Testing
  • Trace points code integrated
  • Unit tests integrated
  • Demo's review

Issues

  • Fast Model slowness - maybe an issue with testing