Timeline for delivery of big.LITTLE Switcher (Task Migration) on Fast Model

Milestones Status

Plan of Record

Milestone

Date

Current

Last Report

Issue

Develop Reference Switcher

3/15/2012

Debugging Switcher is done

Validation Ready

3/29/2012

closure on tests, developing the tests

Validate Ref. Switcher

4/5/2012

Dependent on validation readiness

Develop Integrated Switcher

4/05/2012

New code

Validate Integrated Switcher

4/26/2012

Develop RC-1

5/10/2012

GA Release

5/31/2012

Color Keys

Complete

On target

At risk
mitigation in place

Will miss target
Immediate action required

Blueprints Status

Accomplishments This Week

  • Paul has Test Plan reviewed, ready for approval.
  • Dave has completed Reference Switcher debugging.
  • Vishal has Android booting to full GUI on A15x1-A7x1 and a15x4-A7-x4 Fastmodels.
  • Riku has Fastmodels booting (not with big.Little yet) on Ubuntu, working on creating images using Linaro tools.
  • Joey/Loic got Fast Models Licenses, and infrastructure (FLEXML server )set.

Issues

  • License infrastructure being setup - resolved - thanks to Joey and Loic.
  • Resources issue - Resolved.